The Attorney General petitioned Nov. 13 to intervene for the State in Indiana Michigan Power's request for a certificate to build the 1,520 MW Rockport Energy Center, a natural gas combined cycle plant at its Rockport coal station, and the Commission devoted the Nov. 20 evidentiary hearing to that petition. The State supports the gas plant but argues the Commission "should not grant the certificate on a record that treats the end-of-2028 Rockport retirements as fixed." It asks for a finding that the order does not approve retirement of either coal unit, and for conditions to preserve resource adequacy until the new units enter service in 2030.
A federal consent decree requires Rockport Unit 1 to retire by Dec. 31, 2028, and the company plans to retire Unit 2 as well. The State moved July 31 in U.S. District Court for the Southern District of Ohio to intervene in the consent decree case and modify the Unit 1 retirement obligation. According to the petition, citizen plaintiffs and four plaintiff states opposed that motion Oct. 23, and it remains pending. The State also petitioned Nov. 13 to intervene in I&M's base rate case, objecting to depreciation, dismantlement and deferral treatment that presumes the Rockport retirements.
At the hearing, the Commission questioned the State's counsel on the four months between the company's filing and the petition, on the Attorney General's general powers statute and the parens patriae doctrine the petition relies on, on how the State's interest differs from the OUCC's representation of the public, and on the Supreme Court's 2024 decision in City of Carmel v. Duke Energy Indiana. A commissioner raised certifying the question of the Attorney General's authority to the Court of Appeals, a step the commissioner said the Commission last took in 1979.
The State, the OUCC, the Industrial Group and Citizens Action Coalition said they would not object to a certified question. The company said it would not object so long as the March 17, 2027, statutory deadline for an order could still be met, and it does not object to the intervention itself. The Commission took the petition under advisement and continued the evidentiary hearing to Dec. 1.