The Commission approved amendments to NIPSCO's special contract with Amazon Data Services adding 400 MW of capacity to the original 2,400 MW. The added capacity will be served from a pool of resources NIPSCO's generation affiliate, NiSource Generation Company, is assembling to serve multiple large load customers. NIPSCO estimates the amendments will return an additional $182.5 million to its other retail customers over the 15-year term through the Shared System Credit Mechanism, for an estimated $1.35 billion from the Amazon contract in all. At full ramp, residential electric customers would receive a credit of about $8 a month.
The Industrial Group raised concerns about use of the pooled resources, possible overbuilding and the affiliate's retention of revenue from excess capacity. The Commission found the overbuilding concerns unfounded and the existing affiliate and Amazon settlement provisions sufficient to protect against it, and declined the restrictions the Industrial Group proposed. Citizens Action Coalition asked the Commission to deny or defer approval until transmission studies are complete. The Commission found that request "inapposite and untimely," while noting that studies to date are "high level and preliminary" and that more are expected.
The OUCC did not oppose the amendments but asked for annual updates on transmission studies. The Commission found the Amazon settlement already provides a continuing framework for those studies and accepted NIPSCO's offer of informal semiannual meetings with the OUCC. NIPSCO and its affiliate must file a schedule of planned transmission studies by Dec. 2.